Projects - United Parcel Service - Atlanta, GA
Projects - United Parcel Service - Mahwah, NJ
Projects - Dominion
Projects - Qwest Communications
Projects - American International Group (AIG)
Projects - Berkley Federal Trust Bank
Projects - Blockbuster Entertainment
Projects - Capital One Bank
Projects - Colo.com (Medford, Watertown & Boston, MA & New York, NY )
Projects - Epoch Transaction Services
Projects - Equant Corporation (Formerly Global One)
Projects - NationsBank (Now Bank of America)
Projects - First American Data Company
Projects - Fowler & Flannagan Technologies LLC
Projects - Motorola Corporation
Projects - Reliance Insurance Company
Projects - Quantum Chemical Corporation
Projects- GSA-Mid Atlantic Region
   
See Complete Project List
 
Motorola Corporation
Motorola Corporation
Overview

CSIE was engaged by Motorola to manage and implement the relocation of the Mid-Western Area Computer Center (MACC). The scope of our services included the design of a 3,000 square foot command console, design review for the 70,000 square foot MACC, preliminary site readiness and overall project management for the relocation of the data center and Telecommunications network. CSIE’s fundamental objective was to implement the relocation for the MACC with uninterrupted services and operation of Motorola’s business. Development of the relocation plan involved the migration of four IBM mainframes and associated peripherals. Motorola’s project required worldwide communications network cutover and CSIE developed a plan to provide interim communications services while moving ten front-end processors and their associated communications lines. Services performed by CSIE included: Design review for data center, computer hardware planning, migration planning, migration implementation, telecommunications consulting, testing and facility commissioning, cable management and overall project management.

Project Highlights
  • 70,000 sf data center
  • 3,000 sf command console
  • 400 tons of computer room HVAC
  • 1500 kVA static UPS/battery system
  • 4800 kW diesel generator
  • Halon fire suppression system
  • 415 Hz frequency conversion
  • Project completed 1990 on time/on budget
 
 