Projects - United Parcel Service - Atlanta, GA
Projects - United Parcel Service - Mahwah, NJ
Projects - Dominion
Projects - Qwest Communications
Projects - American International Group (AIG)
Projects - Berkley Federal Trust Bank
Projects - Blockbuster Entertainment
Projects - Capital One Bank
Projects - Colo.com (Medford, Watertown & Boston, MA & New York, NY )
Projects - Epoch Transaction Services
Projects - Equant Corporation (Formerly Global One)
Projects - NationsBank (Now Bank of America)
Projects - First American Data Company
Projects - Fowler & Flannagan Technologies LLC
Projects - Motorola Corporation
Projects - Reliance Insurance Company
Projects - Quantum Chemical Corporation
Projects- GSA-Mid Atlantic Region
   
See Complete Project List
 
Reliance Insurance Company
Reliance Insurance Company
Overview

CSIE designed and implemented this project from start to finish, beginning by developing an overall program for the new data processing facility accounting for a ten-year projected computer hardware growth. The site selection covered the entire eastern United States and took approximately 4 months to complete. Once the site was selected, CSIE began the engineering phase of the project translating the original program to construction document and specifications and then managed the entire effort including the construction and facility commissioning. The overall configuration consists of a 46,000 sf main building (incorporating the 40,000 sf computer center, print room, tape library, paper storage area, communications network control area, command center, support office area, technical expansion area, lounge, dining room, conference room and exercise room with lockers and showers).

Project Highlights
  • 1 story 46, 000 sf main building
  • 1000 kVA status UPS/battery system
  • 2400 kW diesel generator
  • 40,00 sf of 18” raised flooring
  • Halon fire suppression system
  • 633 tons of computer room air conditioning
  • 415 Hz frequency conversion
  • 100 tons of building HVAC and (4) chillers
  • Estimated project cost $10,000,000
  • Project completed 1991 on time/on budget
 
 